MarionVille

PROJECT DETAILS

  • Phase 1 (January – March, 2018): Clearing and Grubbing, Canal Dredging and removal of weathered rock to maintain deep navigational clearance, Cofferdam installation, and Excavation of West Bank within Cofferdam Work Area
  • Phase 2 (April – November, 2018) : Installation of Watermain across East and West Bank, Construction of Earth Dams, Construction of By-Pass Pipe and By-Pass Inlet and Outlet Structures, and Construction of the West Side of Concrete Structure for the Guard Gate.
  • Phase 3 (November 2018 – March 2019) : Cofferdam Installation, Watermain Installation Across the Canal, Construction of East Side of Concrete Structure for Guard Gate, Concrete Apron on the Canal Bed, Stop Sills, Sector Gate Embedded Parts (Gate Sill, Pintles, Vertical Sealing Path), Sector Gate Installation, Electrical Works,
  • Phase 4 (April 2019 – May 2019): Gate Commissioning, Landscaping